Workshop Phase 5.
Installing Ceiling Insulation & Chipboard
Mezzanine Floor.
Synopsis of Work for Installing Ceiling Insulation
& Chipboard Mezzanine Floor.
The first step was to pack rock wool insulation on top
of the ceiling plasterboards between the joists. The
chipboard flooring was then cut to size and screwed to
the top of the joists ensuring that the tongue and
groove joints were fully engaged and that lengthwise,
the boards abutted together above a joist thus ensuring that the
joints were fully supported.
2nd August 2015
Loft insulation purchased.
Details of Loft Insulation installation.
|
Loft Insulation Purchased. 2nd August
2015
Two rolls of 'Rock Wool' insulation were purchased. These are
made from recycled glass. This product comes
partially cut into three widths of 400mm which is
ideal for the 405mm joist spacing adopted for
this project.
(Click picture for larger view)
|
|
Loft Insulation Unpacked, 2nd August 2015
A roll of 100mm thick insulation. The partial
cuts are clearly visible with options for
either cutting in half to give two rolls of 600mm width,
or making two cuts giving three rolls of 400mm width.
The 400mm width option was the preferred one for this project.
(Click picture for larger view)
|
|
Cut to Size, 2nd August
2015
The best course of action before using the
insulation in the confines of the loft, is to use
some scissors to completely cut through the
partial cuts so that three separate rolls of the
correct width are ready for use - as shown in
this photograph.
(Click picture for larger view)
|
|
Installation, 2nd
August 2015
Work in progress installing the loft insulation
between the joists. Work carried out in tandem
with chipboard floor installation. The unfixed
sheets of chipboard flooring provide useful
temporary supports whilst the insulation is
unrolled in position.
(Click picture for larger view)
|
|
Completion, 3rd August
2015
Loft insulation completed and work well under way
in installing the overlying chipboard flooring (See details
below).
(Click picture for larger view)
|
Loft Insulation completed. 3rd August 2015.
Details of Chipboard Floor Installation.
Work commenced 2nd August 2015 in tandem
with installation of partition studwork. Using 10
boards of flooring grade tongue & groove chipboard,
2,400mm x 600mm x 18mm. Each board weighs about 17.3kg.
|
Chipboard Flooring Dimensions.
Estimated that ten boards required, delivered on
the 20th July 2015.
(Click picture for larger view)
|
|
Cutting to Size.
After marking out, the boards were easily cut to
size using a hand-saw. The boards are just
manageable to move by one fit adult but two
people make handling much easier.
(Click picture for larger view)
|
|
Installation, 2nd August
2015.
This was very similar to the installation of the
plasterboards. The positions of the underlying
joists were marked out in pencil on the boards
and then the same wooden template was used to
mark the positions of the screws at 150mm
intervals (this worked out at 4 screws across the
boards for each joist). Screws were 4mm diameter,
45mm long. Where two boards join, it is essential
that the joint is above a joist (as for the
plasterboard sheets), and also essential that the
tongue & groove is also on the joint.
(Click picture for larger view)
|
|
Installing the Last Board. 4th August
2015.
The last narrow row of boards were difficult to
install because of the constraints of the tongue
& groove contacts with the other boards on
one side and the garage wall on the other. It was
found that the easiest way to fit them was to
slide the boards in from the open (garage door
end) of the loft, tapping them gently into place using a wooden mallet.
(Click picture for larger view)
|
|
Completed Mezzanine Floor, 4th August
2015.
Photograph of the completed chipboard floor
(bottom) compared to the floor as envisaged in
the Sketchup design (top).
(Click picture for larger view)
|
Mezzanine Floor completed 4th August 2015.
Replacing & Moving Collar Ties.
To improve access and storage capacity of the mezzanine floor, three of the collar ties (spanning the rafters across the garage above the mezzanine floor), needed either replacing or moving. Two were replaced with lower (& longer) ones, to improve access & capacity, whilst a third, immediately in front of the mezzanine floor, was moved forwards by one rafter to improve ladder access.
It's important to replace and not just
remove the collar ties as they are an important
structural element of the roof.
|
Replacing & Moving Collar Ties.
This sketch plan shows which two collar ties were
removed (pale brown), after the
replacement ties (pale green) had been bolted in
place. It also shows the front collar tie (pale
brown, right of sketch), was moved and replaced
(shown in dark green), one rafter forward. This
was to improve ladder access to the mezzanine
floor.
(Click picture for larger view)
|
|
Replacing & Moving Collar Ties.
4th August 2015.
This photograph shows the two collar ties to be
replaced and, at the front, the collar tie to be
moved.
(Click picture for larger view)
|
|
Replacement Collar Tie Details. 17th
August 2015.
Photograph of one end of a replacement Collar Tie
(45mm x 95mm). The joists were cut to the correct
size and pre-drilled (with one 12mm diameter hole
at each end), to take M12 coach bolts. Bolting was the preferred option rather than nailing.
(Click picture for larger view)
|
|
Fixing a Replacement Collar Tie, 17th
August 2015.
The new collar tie is temporarily held in place with a
clamp. Note that the original collar tie is
still in place (nailed to the rafter), and was
only removed after the new collar tie had been
bolted in place.
(Click picture for larger view)
|
|
Drilling a Fixing Hole,
17th August 2015.
With the new collar tie temporarily clamped in
place, a 12mm hole was drilled through the rafter
using the 12mm pre-drilled hole in the
replacement collar tie as a template.
(Click picture for larger view)
|
|
Bolting in Place. 17th
August 2015.
Replacement collar tie bolted in place. The old
(higher) collar tie, nailed in place, can now be
removed.
(Click picture for larger view)
|
|
Completed, 19th August 2015.
Two new collar ties bolted in place and the old
ties removed.
(Click picture for larger view)
|
|
Moving an Existing Collar Tie,
29th August 2015.
Collar tie moved forward by one pair of rafters
and fixed in position by two M12 coach bolts.
This gave much improved ladder access to the
Mezzanine floor.
(Click picture for larger view)
|
Ceiling insulation and mezzanine floor, completed
29th August 2015.
Click HERE to return to the Home
Page.
© Tim & Trish Enterprises 2015-2017.